6 November 2014
Not really. Chas has been characteristically silent and, only after various prompts, admitted that he is behind schedule. Tell us something new, Chas.
Anyway, he is in the process of sourcing materials (slate and larch) to match those used on the barn, and should be able to finish this week.
In the meantime, here's a photo of the little structure he has built for the expansion tank and pellets storage. Unfortunately, he had to destroy a grape vine that was happily climbing the back left corner. We discussed this in August, so we were well prepared.
And in other, happier news, things are starting to happen for the dépendance. In an email from Tom yesterday:
"...things are now moving with the dependence. I am picking up the A-frame on Monday the 10th November, photo’s (sic) of A-frame/Demolition work/masonry work will be on their way to you by the middle of next week..."
And, as we know, Tom is a man of his word.
No comments:
Post a Comment