On Sunday night, a brief update on La Fromagerie.

Chas left on Thursday at noon, allowing Tom to get in and set up for the screed, which was scheduled for Friday. Tom had decided to use the plasterer's labourers ("getting the screed mix right is quite tricky, they have more experience at mixing traditional screeds (... and also...) that allows me to help level and float-finish the floor with the plasterer). 

"... all the heights worked out exactly how I wanted them to. Four of us screeded all day on Friday, it was hard work but all went according to plan. I’m looking forward to going onto the screed and sweeping it down and tidying up the edges."




Tom is now off on a two-week holiday. In the meantime, Phil will be in to measure up for the stairs and will begin their construction, Brian will return for second electrical fix, and Gregg will get on with making the shutters.